Abington Township, PA
Home MenuGovernment » Office of the Township Manager » Projects » Edge Hill Road and Tyson Avenue Reconstruction Project
Project Updates: Edge Hill Road and Tyson Avenue Reconstruction Project
Construction Updates
UPDATE AS OF JUNE 2, 2021: Edge Hill Road from Tyson Avenue to Bradfield Road is now ONE-WAY.
The following turns will be now prohibited:
-
Left turns onto Edge Hill Road from northbound Bradfield Road
-
Right turns onto Edge Hill Road from southbound Bradfield Road
For general questions, please submit a question through our online portal here. For a specific property question within the project area, please contact PennDOT Inspector in Charge, Ken Seal at kseal@pa.gov or 215-436-4988 or Tim Homan at tihoman@pa.gov or 215-651-0267.
This section will contain monthly updates from the project team on work being conducted and planned. It will be updated as information is provided by PennDOT.
December 2021 Update
Work Performed to Date
Driveway adjustments continued during December. All asphalt wearing course placement is complete throughout the project. Installation of permanent signs as well as permanent line striping is complete. Traffic on Edge Hill Road is now permanently one-way between Tyson Ave. and Bradfield Road.
Upcoming Work to be Performed
In January of 2022, completion of driveway adjustments will take place as weather permits as well as remaining contract items.
New Ardsley SEPTA station driveway apron
Tyson Ave. intersection with Edge Hill Road
Tyson Ave. looking east
Bradfield Road looking north
Edge Hill Road looking west towards Bradfield Road
Edge Hill Road looking east towards Easton Road
August 2021 Update
Work Performed to Date
Driveway adjustments continued during August. All asphalt wearing course placement is complete throughout the project. Installation of permanent signs continues as well as permanent line striping and is 95% complete. Traffic on Edge Hill Road is now permanently one-way between Tyson Ave. and Bradfield Road.
Upcoming Work to be Performed
In September of 2021, completion of driveway adjustments will take place as well as remaining contract items. The contractor will complete all final line striping and installation of all permanent signs.
Edge Hill Road looking west towards Ardsley Avenue.
Edge Hill Road looking east towards Custer Avenue.
Edge Hill Road looking east from Custer Avenue.
Tyson Avenue looking east towards Bradfield Road.
Tyson Avenue looking east between Custer Avenue and Bradfield Road.
Edgecomb Avenue looking south from Tyson Avenue.
Ardsley Avenue looking south from Tyson Avenue.
New traffic signals at the intersection of Edge Hill Road and Easton Road.
July 2021 Update
Work Performed to Date
Installation of resident steps and landscape retaining walls continued during July. Construction of new concrete curb and sidewalk continued at the intersection of Tyson Ave. and Easton Road and at the intersection of Tyson Ave. and Jenkintown Road. All asphalt wearing course placement is complete throughout the project. Installation of permanent signs has started as well as permanent line striping and is 95% complete. Traffic on Edge Hill Road is now permanently one-way between Tyson Ave. and Bradfield Road.
Upcoming Work to be Performed
In August of 2021, completion of landscape retaining walls and driveway adjustments will take place as well as remaining contract items. The contractor will complete all final line striping and installation of all permanent signs.
Final asphalt wearing course pavement with line striping on Bradfield Road looking south.
Final asphalt wearing course pavement with line striping and new signs on Edge Hill Road looking towards Bradfield Road.
New traffic signals and signs on Jenkintown Road at the SEPTA Ardsley station parking lot.
New traffic signals and signs on Jenkintown Road at the SEPTA Ardsley station parking lot looking west.
New traffic signals and signs at the intersection of Tyson Ave. and Jenkintown Road looking west.
New traffic signals and signs at the intersection of Easton Road and Edge Hill Road.
Final asphalt wearing course pavement on Bruce Road looking south.
Final asphalt wearing course pavement on Bruce Road looking north.
June 2021 Update
Work Performed to Date
Installation of resident steps and landscape retaining walls continued during June. Placement of topsoil and grass seed took place on Edge Hill Road. Construction of new concrete curb and sidewalk continued at the intersection of Tyson Ave. and Easton Road and at the intersection of Tyson Ave. and Jenkintown Road. All asphalt wearing course placement is complete throughout the project. Installation of permanent signs has started as well as permanent line striping. Traffic on Edge Hill Road is now permanently one-way between Tyson Ave. and Bradfield Road.
Upcoming Work to be Performed
In July of 2021, completion of landscape retaining walls and driveway adjustment will take place as well as remaining contract items. The contractor will complete all final line striping and installation of all permanent signs.
Final asphalt wearing course pavement with line striping on Edge Hill Road looking west between Tyson Ave. and Ardsley Ave.
Final asphalt wearing course pavement with line striping and new signs on Edge Hill Road looking west from Custer Ave.
Final asphalt wearing course pavement with line striping on Edge Hill Road looking east between Custer Ave. and Bradfield Road.
Final asphalt wearing course pavement with line striping and signs on Edge Hill Road looking east towards Bradfield Road.
Final asphalt wearing course pavement with line striping on Edge Hill Road looking east towards Easton Road.
Final asphalt wearing course pavement with line striping on Tyson Ave. looking west towards Custer Ave.
Final asphalt wearing course pavement with line striping on Tyson Ave. looking west between Easton Road and Bradfield Road.
Final asphalt wearing course pavement with line striping on Tyson Ave. looking east between Easton Road and Bradfield Road.
Final asphalt wearing course pavement with line striping on Ardsley Ave. looking south.
Final asphalt wearing course pavement with line striping on Edgecomb Ave. looking south.
Final asphalt wearing course pavement with line striping on Custer Ave. looking south.
Final asphalt wearing course pavement with line striping on Bradfield Road looking north.
May 2021 Update
Work Performed to Date
Installation of resident steps and landscape retaining walls continued during May. Placement of topsoil and grass seed took place on Edge Hill Road. Construction of new concrete curb and sidewalk continued at the intersection of Tyson Ave. and Easton Road and at the intersection of Tyson Ave. and Jenkintown Road. Full depth roadway reconstruction is complete on Edge Hill Road between Bradfield Road and Easton Road with the exception of placement of the final asphalt course. Paving of the final asphalt wearing course has started on Tyson Ave., Edge Hill Road and the side streets and is 75% complete.
Upcoming Work to be Performed
In June of 2021, construction of new concrete curb and sidewalk will continue at various locations throughout the project. Paving of the final asphalt wearing course will continue on Edge Hill Road, Tyson Ave. and Jenkintown Road. Installation of permanent signs will start as well as final line striping of the roadways.
Final asphalt wearing course pavement looking east of Tyson Ave. at Custer Ave.
Final asphalt wearing course pavement on Tyson Ave. looking west
Final asphalt wearing course pavement on Tyson Ave. looking east
Final asphalt wearing course pavement on Edge Hill Rd. looking west from Ardsley Ave.
Final asphalt wearing course pavement on Edge Hill Rd. looking east from Ardsley Ave.
Final asphalt wearing course pavement on Edge Hill Rd. at the intersection of Edgecomb Ave.
Final asphalt wearing course pavement on Ardsley Ave. looking north
Final asphalt wearing course pavement on Edgecomb Ave. looking north
April 2021 Update
Work Performed to Date
Installation of resident steps and landscape retaining walls continued during April. Traffic signal test has started at the intersection of Edge Hill Road and Easton Road. Construction of new concrete curb and sidewalk continued on Edge Hill Road between Custer Ave. and Bradfield Road. Full depth roadway reconstruction started on Edge Hill Road between Bradfield Road and Easton Road as well as new concrete curb and sidewalk.
Upcoming Work to be Performed
In May of 2021, construction of new concrete curb and sidewalk will continue on Edge Hill Road between Custer Ave. and Easton Road. Traffic signal testing will take place on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway. Roadway re-construction on Edge Hill Road between Bradfield Road and Easton Road will continue. Paving of the final asphalt wearing course will start on Edge Hill Road and Tyson Ave.
Roadway reconstruction on Edge Hill Road between Bradfield Road and Easton Road looking east.
New concrete curb and roadway construction at the intersection of Bradfield Road and Edge Hill Road
Roadway paving and new concrete curb and sidewalk looking west on Edge Hill Road between Custer Avenue and Bradfield Road
New sidewalk on Edge Hill Road between Bradfield Road and Easton Road
March 2021 Update
Work Performed to Date
Installation of resident steps and landscape retaining walls re-started during February. Traffic signal pole, mast arm installation and foundation construction took place on Jenkintown Road at the SEPTA train station parking lot and at the intersection of Edge Hill Road and Easton Road.
Upcoming Work to be Performed
In March of 2021, construction of landscape retaining walls and step and railing installation will continue on Edge Hill Road between Custer Ave. and Bradfield Road. Traffic signal construction will continue on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway and at the intersection of Edge Hill Road and Easton Road. Sidewalk and curb construction on Edge Hill Road will restart in March of 2021 as the weather permits. Roadway construction on Edge Hill Road between Bradfield Road and Easton Road will take place.
Roadway paving and new concrete curb and sidewalk on Custer Ave. looking north from Edge Hill Road.
New landscape wall, steps, and railings on Edge Hill Road
Roadway paving and new concrete curb on Edge Hill Road at Bradfield Road looking east.
New traffic signal construction at the intersection of Edge Hill Road and Easton Road.
January 2021 Update
Work Performed to Date
As of December 31, 2020, curb and sidewalk construction is ongoing on Edge Hill Road between Custer Ave. and Bradfield Road. Roadway paving of the first two courses of asphalt is complete on Edge Hill Road between Tyson Ave. and Bradfield Road. Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Installation of new traffic signal poles and mast arms is ongoing on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway. Construction of new traffic signal foundations and poles is ongoing at the intersection of Edge Hill Road and Easton Road.
Upcoming Work to be Performed
In January of 2021, curb and sidewalk construction and driveway adjustments will continue on Edge Hill Road between Custer Ave. and Bradfield Road as well as construction of landscape retaining walls as the weather permits. Traffic signal construction will continue on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway and at the intersection of Bradfield Road and Easton Road.
Roadway paving on Edge Hill Road between Custer Avenue and Bradfield Road looking west
Roadway paving, new concrete curb, and driveway adjustments on Edge Hill Road between Custer Avenue and Bradfield Road looking east
Roadway paving and new concrete curb on Edge Hill Road between Custer Avenue and Bradfield Road looking east
Traffic signal construction at the intersection of Edge Hill Road/SEPTA lot and Jenkintown Road
Traffic signal construction at the intersection of Tyson Avenue and Jenkintown Road
December 2020 Update
Contractor Look Ahead
Three week look ahead, November 30, 2020 - December 20, 2020
Work Performed to Date
As of November 30, 2020, the contractor has completed drainage construction on Edge Hill Road between Custer Ave. and Bradfield Road. Curb and sidewalk construction is ongoing on Edge Hill Road between Custer Ave. and Bradfield Road. Roadway paving of the first two courses of asphalt has taken place on Edge Hill Road to approximately 500 feet east of Custer Ave. Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Installation of new traffic signal poles and mast arms is ongoing on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway. Construction of new traffic signal foundations is ongoing at the intersection of Edge Hill Road and Easton Road.
Upcoming Work to be Performed
In December of 2020, curb and sidewalk construction and driveway adjustments will continue on Edge Hill Road between Custer Ave. and Bradfield Road as well as construction of landscape retaining walls. Asphalt paving on Edge Hill Road up to Bradfield Road will take place. Traffic signal construction will continue on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway.
Roadway paving on Edge Hill Road at Custer Avenue looking west
Roadway paving on Edge Hill Road between Custer Avenue and Bradfield Road looking west
Concrete curb construction on Edge Hill Road between Custer Avenue and Bradfield Road looking west
Roadway subbase construction on Edge Hill Road west of Bradfield Road looking east
November 2020 Update
Contractor Look Ahead
Work Performed to Date
As of October 31, 2020, the contractor has continued with drainage construction on Edge Hill Road between Custer Ave. and Bradfield Road. Sidewalk construction is ongoing on Tyson Ave. at the side streets. Curb and sidewalk construction is ongoing on Edge Hill Road between Tyson Ave. and Custer Ave. Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Placement of topsoil and grass seed adjacent to new sidewalk is ongoing. Construction of new sidewalk at the intersection of Tyson Ave. and Jenkintown Road has taken place. Installation of new traffic signal poles and mast arms is ongoing on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway. Construction of new traffic signal foundations is ongoing at the intersection of Edge Hill Road and Easton Road.
Upcoming Work to be Performed
In November of 2020, curb and sidewalk construction and driveway adjustments will continue on Edge Hill Road between Tyson Ave. and Custer Ave. as well as construction of landscape retaining walls. Drainage construction will continue on Edge Hill Road between Custer Ave. and Bradfield Road. Construction of new curb, sidewalk and roadway will start between Custer Ave. and Bradfield Road. Driveway adjustments will take place on Tyson Ave. and Edge Hill Road as well as roadside development. Traffic signal construction will continue on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway as well as at the intersection of Edge Hill Road and Easton Road.
Edge Hill Road roadway construction and roadside development looking west towards Tyson Avenue
New roadway and curb construction on Edge Hill Road just west of Custer Avenue
New drainage inlets on Edge Hill Road just west of Custer Avenue
New drainage inlets on Edge Hill Road between Custer Avenue and Bradfield Road
Drainage construction on Edge Hill Road just west of Bradfield Road
New traffic signal controller cabinet and pole at the intersection of Tyson Ave. and Jenkintown
Contractor Look Ahead
Click here to view the August 31, 2020 to September 20, 2020 three week look ahead.
Work Performed to Date
As of September 30, 2020, the contractor has continued with drainage construction on Edge Hill Road between Custer Ave. and Bradfield Road. Sidewalk construction is ongoing on Tyson Ave. at the side streets. Curb and sidewalk construction is ongoing on Edge Hill Road between Tyson Ave. and Custer Ave. Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Placement of topsoil and grass seed adjacent to new sidewalk is ongoing. Construction of new sidewalk at the intersection of Tyson Ave. and Jenkintown Road has taken place. Construction of new traffic signal foundations is ongoing on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway.
Upcoming Work to be Performed
In October of 2020, curb and sidewalk construction and driveway adjustments will continue on Edge Hill Road between Tyson Ave. and Custer Ave. as well as construction of landscape retaining walls. Drainage construction will take place on Edge Hill Road between Custer Ave. and Bradfield Road. Driveway adjustments will take place on Tyson Ave. and Edge Hill Road as well as roadside development. Traffic signal construction will continue on Jenkintown Road at the intersections of Tyson Ave. and Edge Hill Road/SEPTA driveway.
Construction Progress Photos:
Edge Hill Road roadway construction looking east from Tyson Avenue
|
|
New roadway and curb construction on Edge Hill Road looking east towards Custer Avenue
|
Removal of existing roadway on Edge Hill Road looking west towards Custer Avenue
|
Ardsley Avenue construction looking south from Tyson Avenue
|
Driveway adjustments on Edge Hill Road
|
New landscape retaining walls and steps on Edge Hill Road
|
New roadway and curb construction on Tyson Avenue east of Jenkintown Road
|
New roadway and curb construction on Jenkintown Road south of Tyson Avenue
|
September 2020 Update
Contractor Look Ahead
Click here to view the August 31, 2020 to September 20, 2020 three week look ahead.
Work Performed to Date
As of August 31, 2020, the contractor has continued with drainage construction on Edge Hill Road between Tyson Ave. and Custer Ave. Sidewalk construction is ongoing on Tyson Ave. at the side streets. Curb and sidewalk construction is ongoing on Edge Hill Road between Tyson Ave. and Custer Ave. Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Roadway construction continues on Ardsley Ave. Relocation of gas service laterals continues on Edge Hill Road.
Upcoming Work to be Performed
In September of 2020, curb and sidewalk construction and driveway adjustments will continue on Edge Hill Road between Tyson Ave. and Custer Ave. as well as construction of landscape retaining walls. Paving of the first two courses of asphalt roadway will take place on Edge Hill Road between Tyson Ave. and Custer Ave. and on Ardsley Ave. Relocation of gas service will continue on Edge Hill Road.
Ardsley Avenue roadway construction looking south from Tyson Avenue
New roadway and curb construction on Edge Hill Road looking west
New roadway and curb construction on Edge Hill Road looking east
Roadway and curb construction at the intersection of Edge Hill Road and Edgecomb Avenue
New roadway and curb construction on Edge Hill Road looking east towards Custer Avenue
New roadway and curb construction on Edge Hill Road looking east of Edgecomb Avenue
August 2020 Update
UPDATE: Due to extreme heat and for the safety of the workforce, the project crews will start at 6:30 AM beginning Monday, August 3, 2020 for at least a week. We apologize for any inconvenience this may cause.
Contractor Look Ahead
Click here to view the August 5 - August 23, 2020 three week look ahead.
Work Performed to Date
As of July 31, 2020, the contractor has started drainage construction on Edge Hill Road between Tyson Ave. and Custer Ave. Sidewalk construction is ongoing on Tyson Ave. at the side streets. Drainage and curb construction is complete at the intersection of Jenkintown Road and Tyson Ave.
Installation of new concrete steps and walkways at resident properties continues on Edge Hill Road as well as landscape retaining walls. Curb, sidewalk and roadway construction on Custer Ave. is 90% complete. Roadway construction has started on Ardsley Ave. Relocation of gas service laterals has restarted on Edge Hill Road.
Upcoming Work to be Performed
In August of 2020, drainage construction will continue on Edge Hill Road between Tyson Ave. and Custer Ave. and curb and sidewalk construction will take place. Construction of landscape retaining walls will continue on Edge Hill Road. Roadway construction will continue on Ardsley Ave. Relocation of gas service laterals will continue on Edge Hill Road.
New concrete curb on Jenkintown Road
New drainage construction on Edge Hill Road west of Ardsley Avenue
Ardsley Avenue roadway construction looking sound from Tyson Avenue
Drainage construction on Edgecomb Avenue at Edge Hill Road
Milled existing roadway on Edge Hill Road looking east toward Custer Avenue
New concrete steps and landscape retaining wall on Edge Hill Road
July 2020
UPDATE: Due to extreme heat and for the safety of the workforce, the project crews will start at 6:30 AM beginning Monday, August 3, 2020 for at least a week. We apologize for any inconvenience this may cause.
Contractor Look Ahead
Click here to view the July 6 - July 26, 2020 three week look ahead.
Work Performed to Date
As of June 30, 2020, the contractor has completed all drainage work on Tyson Ave. 90% of construction of concrete curb and sidewalk is complete on the north and south side of Tyson Ave. between Edge Hill Road and Easton Road. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to Easton Road. Installation of new concrete steps and walkways at resident properties has started. Curb, sidewalk and roadway construction has started on Custer Ave.
Upcoming Work to be Performed
In July of 2020, curb and sidewalk construction will take place at the side road intersections on Tyson Ave. Relocation of gas service laterals is expected to restart on Edge Hill Road. Construction of drainage, curb, sidewalk and roadway will take place at the west end of Tyson Ave. at Jenkintown Road. After curb and sidewalk is complete on Tyson Ave., re-construction on Edge Hill Road will start utilizing a detour. Curb, sidewalk and placement of the first two courses of asphalt will be completed on Custer Ave.
Tyson Avenue roadway construction looking west from Easton Avenue
Custer Avenue roadway construction looking south from Tyson Avenue
Bruce Avenue curb and roadway construction looking south from Tyson Avenue
Bruce Avenue curb and roadway construction looking north from Edge Hill Road
New sidewalk construction on Tyson Avenue at Bruce Road
New concrete steps on Tyson Avenue
Driveway adjustment on Tyson Avenue
New walkway and step installation on Tyson Avenue
June 2020
Work Performed to Date
Work resumed on the project on May 1, 2020. As of May 31, 2020, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Easton Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Easton Road. Curb and sidewalk construction on the north side is 90% complete up to Bradfield Road. Curb, sidewalk and roadway construction on the south side of Tyson Ave. between Bradfield Road and Easton Road is ongoing. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. Construction of landscape retaining walls is complete on Tyson Ave. The utility companies have completed relocation of gas and water services to individual resident properties on Tyson Ave. Installation of all three new drainage crossings under the SEPTA tracks is complete.
Upcoming Work to be Performed
In June of 2020, curb, sidewalk and roadway construction will continue including asphalt paving on the south and north side of Tyson Ave. up to Easton Road. Relocation of gas service laterals is expected to restart on Edge Hill Road. Construction of drainage, curb, sidewalk and roadway will take place at the west end of Tyson Ave. at Jenkintown Road. After curb, sidewalk and paving of asphalt binder course is complete on Tyson Ave., construction on Edge Hill Road will start utilizing a detour.
Tyson Avenue roadway construction looking west from Bradfield Road
Milling of existing pavement on Tyson Avenue at Easton Road
Roadway subbase grading on Tyson Avenue between Bradfield and Easton Roads
Roadway construction at the intersection of Bradfield Road and Tyson Avenue
Roadway construction on Tyson Avenue between Bradfield and Easton Roads looking west
Roadway construction at the intersection of Tyson Avenue and Easton Road
Construction is expected to resume on Monday, March 4, 2020. Due to COVID-19 and social distancing practices, the public is not to interact in-person with project personnel. For general questions, please submit a question through our online portal here. For a specific property question within the project area, please contact PennDOT Inspector in Charge, Ken Seal at 215-436-4988.
Please be aware that vehicles parked on Tyson Avenue between Carson Avenue and Bradfield Road will need to be relocated to allow for roadway work to continue.
April 2020
Three-week Look Ahead
Due to the Governor's mandate, the project site has been shut down since March 13, 2020. The site will be shut down until Monday, May 4, 2020.
Work Performed to Date
As of March 31, 2020, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Bradfield Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb and sidewalk construction on the north side is 90% complete up to Bradfield Road. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. Construction of landscape retaining walls continued on Tyson Ave. The utility companies have completed relocation of gas and water services to individual resident properties on Tyson Ave. Installation of drainage on Tyson Ave. at Easton Road has started. Line striping on Tyson Ave. between Edge Hill Road and Carson Ave. took place with two-way traffic shifted to the middle of Tyson Ave. Reconstruction of the south side of Tyson Ave. just west of Bradfield Road started. Gas service relocations continued on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete.
Upcoming Work to be Performed
Work on the project has stopped as a result of a directive from the Governor of Pennsylvania due to the Coronavirus. Once work resumes, drainage work will continue at the east end of Tyson Ave. and at Jenkintown Road. Relocation of gas service laterals will resume. Construction of curb, sidewalk and roadway will resume on the east end of Tyson Ave. Construction of landscape retaining walls will resume on Tyson Ave. After curb, sidewalk and paving of binder course is complete on Tyson Ave., construction at the west end of Edge Hill Road will start utilizing a detour.
Traffic shift to the middle of Tyson Avenue between Ardsley Avenue and Edgecomb Avenue looking west.
Traffic shift to the middle of Tyson Avenue between Ardsley Avenue and Edgecomb Avenue looking east.
Traffic shift to the middle of Tyson Avenue between Custer Avenue and Carson Avenue looking west.
Traffic shift to the middle of Tyson Avenue between Custer Avenue and Carson Avenue looking east.
March 2020
Three-week Look Ahead
Due to the Governor's mandate, the project site has been shut down since March 13, 2020. The site will be shut down until further notice.
Work Performed to Date
As of February 28, 2020, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Bradfield Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb and sidewalk construction on the north side is 90% complete up to Bradfield Road. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. The utility companies have completed relocation of gas and water services to individual resident properties on Tyson Ave. Gas service relocations are continuing on Edge Hill Road. Utility pole and aerial service relocations will continue on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete.
Upcoming Work to be Performed
In March of 2020, the contractor will continue drainage construction on both sides of Tyson Ave. between Bradfield Road and Easton Road, on Tyson Ave. between Jenkintown Road and Edge Hill Road and on Edge Hill Road between Tyson Ave and Ardsley Ave. as weather permits. Water service, gas service and utility pole relocations will continue on Edge Hill Road. New concrete curb and sidewalk construction will continue on the south side of Tyson Ave. between Custer Ave. and Bradfield Road as weather permits. Two-way traffic will be maintained on Tyson Ave. between Edge Hill Road and Easton Road. Edge Hill Road will be detoured onto Tyson Ave. between Tyson Ave. and Edgecomb Ave.
Landscape retaining wall construction at the intersection of Tyson Avenue and Custer Avenue.
Ongoing reconstruction of Bruce Ave. looking from Tyson Avenue.
Ongoing reconstruction of Bruce Ave. looking from Edge Hill Road.
Ongoing reconstruction of Edgecomb Avenue looking toward Edge Hill Road
Utility relocation work on Edge Hill Road east of Custer Avenue
February 2020
Three-week Look Ahead
Work Performed to Date
As of January 31, 2020, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Bradfield Road and has started drainage between Bradfield Road and Easton Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb and sidewalk construction on the north side is 90% complete up to Bradfield Road. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. The utility companies have completed relocation of gas and water services to individual resident properties on Tyson Ave. Gas service relocations are continuing on Edge Hill Road. Utility pole and aerial service relocations will continue on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete.
Upcoming Work to be Performed
In February of 2020, the contractor will continue drainage construction on both sides of Tyson Ave. between Bradfield Road and Easton Road and start drainage construction on Edge Hill Road between Tyson Ave and Ardsley Ave. as weather permits. Water service, gas service and utility pole relocations will continue on Edge Hill Road. New concrete curb and sidewalk construction will continue on the south side of Tyson Ave. between Custer Ave. and Bradfield Road as weather permits. Two-way traffic will be maintained on Tyson Ave. between Edge Hill Road and Easton Road. Edge Hill Road will be detoured onto Tyson Ave. between Tyson Ave. and Edgecomb Ave.
Asphalt pavement, curb, and sidewalk construction on Tyson Ave. east of Custer Ave.
Ongoing reconstruction of Bruce Ave. looking south from Tyson Ave.
Asphalt pavement, curb, and sidewalk construction on Tyson Ave. east of Edgecomb Ave.
Asphalt pavement, curb, and sidewalk construction on Tyson Ave. west of Bradfield Rd.
Ongoing reconstruction of Custer Ave. looking towards Tyson Ave.
Utility relocation work on Edge Hill Rd. between Tyson Ave. and Ardsley Ave.
January 2020
Three-week Look Ahead
Work Performed to Date
As of December 31, 2019, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Bradfield Road and has started drainage between Bradfield Road and Easton Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb and sidewalk construction on the north side is complete up to Bradfield Road. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. The utility companies have completed relocation of water services to individual resident properties on Tyson Ave. Gas service relocations are continuing on Edge Hill Road. Utility pole and aerial service relocations will continue on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete. Asphalt driveway and sidewalk adjustments continued on Tyson Ave. Reconstruction of other side roads is ongoing.
Upcoming Work to be Performed
In January of 2020, the contractor will continue drainage construction on both sides of Tyson Ave. between Bradfield Road and Easton Road and start drainage construction on Edge Hill Road between Tyson Ave and Ardsley Ave. Water service, gas service and utility pole relocations will continue on Edge Hill Road. New concrete curb and sidewalk construction will continue on the south side of Tyson Ave. between Custer Ave. and Bradfield Road as weather permits. Two-way traffic will be maintained on Tyson Ave. between Edge Hill Road and Easton Road. Edge Hill Road will be detoured onto Tyson Ave. between Tyson Ave. and Edgecomb Ave.
Drainage construction on Tyson Ave. east of Bradfield Rd.
Asphalt pavement, curb, and sidewalk construction on Tyson Ave. west of Bradfield Rd.
Ongoing reconstruction of Custer Ave. looking south from Tyson Ave.
New asphalt, curb and sidewalk construction on Edgecomb Avenue
Ongoing reconstruction of Ardsley Ave. looking towards Edge Hill Rd.
New asphalt pavement for SEPTA jack and bore access road
December 2019
Work Performed to Date
As of November 30, 2019, the contractor has installed all drainage on Tyson Ave. between Edge Hill Road and Bradfield Road. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb construction on the north side is complete up to Bradfield Road and sidewalk construction is complete up to Carson Ave. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. from Edge Hill Road to just west of Bradfield Road. The utility companies are continuing with relocation of water services to individual resident properties on Tyson Ave. Gas service relocations have started on Edge Hill Road. Utility pole and aerial service relocations will continue on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete. Asphalt driveway and sidewalk adjustments continued on Tyson Ave. Concrete curb, sidewalk and the first two courses of asphalt have been placed on Edgecomb Road. Reconstruction of other side roads is ongoing.
Upcoming Work to be Performed
In December of 2019, the contractor will continue drainage construction on both sides of Tyson Ave. between Bradfield Road and Easton Road. Water service, gas service and utility pole and service relocations will continue on Tyson Ave. and Edge Hill Road. New concrete curb and sidewalk construction will continue between Custer Ave. and Bradfield Road as weather permits. Two-way traffic will be maintained on Tyson Ave. between Edge Hill Road and Easton Road with daytime detours of through traffic on Tyson Ave.
November 2019
Work Performed to Date
As of October 31, 2019, the contractor has installed drainage on Tyson Ave. between Edge Hill Road and Carson Ave. 90% of construction of concrete curb and sidewalk is complete on the south side of Tyson Ave. between Edge Hill Road and Carson Ave. Curb construction of the north side is complete up to Carson Ave. and sidewalk construction is complete up to Bruce Ave. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. between Edge Hill Road and Carson Ave. The utility companies are continuing with relocation of water and gas services to individual resident properties. Utility pole and aerial service relocations will continue on Edge Hill Road. Installation of all three new drainage crossings under the SEPTA tracks is complete. Asphalt driveway and sidewalk adjustments are continuing on Tyson Ave. Reconstruction of side roads is ongoing.
Upcoming Work to be Performed
In November of 2019, the contractor will continue drainage construction on both sides of Tyson Ave. between Carson Ave. and Bradfield Road. Water service, gas service and utility pole and service relocations will continue on Tyson Ave. and Edge Hill Road. New asphalt roadway pavement will be constructed between Carson Ave. and Bradfield Road as well as new concrete curb and sidewalk construction in this area. Driveway adjustments will continue on Tyson Ave. Two-way traffic will be maintained on Tyson Ave. between Edge Hill Road and Easton Road.
Three Week Look Ahead
Meetings
Video: Town Hall Meeting, September 17, 2019
New concrete curb and sidewalk construction on the north and south side of Tyson Ave.
New asphalt pavement on Tyson Ave. east and west of Edgecomb Avenue
New asphalt pavement and drainage construction on Tyson Avenue
New concrete curb and asphalt pavement on Edgecomb Road and new concrete curb on Bruce Avenue
October 2019
Work Performed to Date
As of September 30, 2019, the contractor has installed drainage on the south side of Tyson Ave. between Custer Ave. and Carson Ave. and on the north side of Tyson Ave. between Bruce Ave. and Custer Ave. Construction of concrete curb and sidewalk continues in these areas also. Asphalt paving of the first two courses is complete on the north and south side of Tyson Ave. between Edge Hill Road and Custer Ave. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole and aerial service relocations will continue on Edge Hill Road and Tyson Ave. as well as side roads. Installation of all three new drainage crossings under the SEPTA tracks is complete. Asphalt driveway adjustments were made on Tyson Ave.
Upcoming Work to be Performed
In October, the contractor will continue drainage construction on both sides of Tyson Ave. between Custer Ave. and Carson Ave. Water main, gas main and utility pole and service relocations will continue. New asphalt roadway pavement will be constructed between Custer Ave. and Carson Ave. as well as new concrete curb and sidewalk construction. Driveway adjustments will continue on Tyson Ave. One-way traffic eastbound will be maintained on Tyson Ave. between Edge Hill Road and Ardsley Ave. with two-way local traffic between Ardsley Ave. and Easton Road.
Three Week Look Ahead
Meetings
Video: Town Hall Meeting, September 17, 2019
New concrete curb and sidewalk construction on the north side of Tyson Ave.
New asphalt pavement on Tyson Ave. west of Custer Ave. and ground stabilization in Hillside Cemetery at SEPTA Crossing No. 1
Driveway adjustment on Tyson Ave. and new concrete curb and sidewalk construction on the south side of Tyson Ave.
September 2019
SEPTA Track Drainage Installation (Updated September 6, 2019)
Drilling and jacking work under the SEPTA tracks at three separate locations will begin Friday, July 12, 2019. Work has been postponed on the completion of Crossing 3. The work at each of the three locations will start on a Friday night at 6:00 pm and will be completed Sunday night. Due to unexpected delays, work has been postponed.
The UPDATED schedule will be as follows:
- Crossing No. 3 TENTATIVE: Work has not yet been scheduled. This crossing is behind 854 and 860 Tyson Avenue.
Work Performed to Date
As of August 31, 2019, the contractor installed drainage on the south side of Tyson Ave. between Custer Ave. and Bradfield Road and on the north side of Tyson Ave. between Edgecomb Ave. and Custer Ave. Construction of concrete curb and sidewalk continues in these areas also. Asphalt paving of the first two courses is complete on the south side of Tyson Ave. between Edge Hill Road and Bruce Ave. and on the north side between Edge Hill Road and Custer Ave. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole and aerial service relocations will continue on Edge Hill Road and Tyson Ave. as well as side roads. Installation of two of three new drainage crossings under the SEPTA tracks is complete.
Upcoming Work to be Performed
In September, the contractor will continue drainage construction on the south side of Tyson Ave. between Custer Ave. and Bradfield Road and on the north side of Tyson Ave. between Custer Ave. and Bruce Ave. Installation of the last drainage crossing under the SEPTA tracks will take place in September. Water main, gas main and utility pole and service relocations will continue. New concrete curb and sidewalk construction will continue on the north side of Tyson Ave. Edgecomb Ave. and Custer Ave. One-way traffic eastbound will be maintained on Tyson Ave. between Edge Hill Road and Ardsley Ave. with two-way local traffic between Ardsley Ave. and Easton Road.
Three Week Look Ahead
Meetings
Video: Town Hall Meeting, September 17, 2019
New concrete curb and sidewalk construction and asphalt on the north side of Tyson Ave.
Asphalt paving on the south side of Tyson Avenue east of Bruce Avenue and north side of Tyson Ave. east of Edgecomb Avenue
Drainage manhole south of the SEPTA tracks at crossing No. 2 and ground stabilization in Hillside Cemetery at SEPTA Crossing No. 1
Milling of existing asphalt roadway on Tyson Avenue and aerial utility relocation on Edge Hill Road
August 2019
Work Performed to Date
As of July 31, 2019, the contractor is continuing with drainage installation on the south side of Tyson Ave. between Custer Ave. and Bradfield Road and on the north side of Tyson Ave. between Edge Hill Road and Edgecomb Ave. Construction of concrete curb and sidewalk continues in these areas also. Asphalt paving of the first two courses is complete on the south side of Tyson Ave. between Edge Hill Road and Custer Ave. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole and aerial service relocations will continue on Edge Hill Road and Tyson Ave. as well as side roads. Installation of the first of three new drainage crossings under the SEPTA tracks is complete. Construction of the Restorative Conveyance drainage swale is complete in Hillside cemetery.
Upcoming Work to be Performed
In August, the contractor will continue drainage construction on the south side of Tyson Ave. between Custer Ave. and Bradfield Road and on the north side of Tyson Ave. between Edge Hill Road and Edgecomb Ave. Installation of the two remaining drainage crossings under the SEPTA tracks will take place in August. Water main, gas main and utility pole and service relocations will continue. New concrete curb and sidewalk construction will continue on the north side of Tyson Ave. between Edge Hill Road and Ardsley Ave. One‐way traffic eastbound will be maintained on Tyson Ave. between Edge Hill Road and Ardsley Ave. with two‐way local traffic between Ardsley Ave. and Easton Road.
New concrete curb construction on the north side of Tyson Avenue and new sidewalk and curb construction on the south side of Tyson Ave.
Drainage manhole installation of Tyson Avenue and asphalt paving on Tyson Ave. west of Custer Avenue
Aerial utility relocation on Tyson Avenue and new drainage pipe under the SEPTA tracks
July 2019
Work Performed to Date
As of June 28, 2019, the contractor is continuing with drainage installation on Tyson Ave. between Bruce Ave. and Custer Ave. as well as on side roads between Tyson Ave. and Edge Hill Road. Construction of concrete curbs and sidewalks has started on the south side of Tyson Ave. between Edge Hill Road and Custer Ave. Asphalt paving of the new roadway has started on the south side of Tyson Ave. between Edge Hill Road and Custer Ave. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole relocations will continue on Edge Hill Road and Tyson Ave. as well as side roads.
Upcoming Work to be Performed
In July, the contractor will continue drainage construction on Tyson Ave. between Custer Ave. and Bradfield Road and the side roads between Tyson Ave. and Edge Hill Road. New drainage installation under the SEPTA railroad tracks will start. Water and gas main and utility pole relocations will continue. New concrete curb and sidewalk construction will continue on Tyson Ave. Placement of new asphalt roadway on the south side of Tyson Ave between Edgecomb Ave and Custer Ave. will continue. Traffic on sections of Tyson Ave. will be closed to all traffic except local traffic.
New concrete curb construction on the south side of Tyson Ave. and new roadway subbase construction on Tyson Ave.
Asphalt paving on the south side of Tyson Ave. between Edge Hill Road and Ardsley Ave. and Hillside Drive in the Cemetery
Regenerative stormwater conveyance in Hillside property and new concrete sidewalk curb on the south side of Tyson Ave
June 2019
Work Performed to Date
As of May 31, 2019, the contractor is continuing with drainage installation on Tyson Ave. between Bruce Ave. and Custer Ave. as well as on side roads between Tyson Ave. and Edge Hill Road. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole relocations will continue on Edge Hill Road and Tyson Ave. as well as side roads.
Upcoming Work to be Performed
In June, the contractor will continue drainage construction on Tyson Ave. and the side roads between Tyson Ave. and Edge Hill Road. New drainage installation under the SEPTA railroad tracks will start. Water and gas main and utility pole relocations will continue. New concrete curb construction will continue, and sidewalk construction will start on the south side of Tyson Ave. between Edge Hill Road and Custer Ave. Placement of new asphalt roadway on the south side of Tyson Ave between Edge Hill Road and Custer Ave. will start. Traffic on sections of Tyson Ave. will be closed to all traffic except local traffic.
New liner for existing drainage pipe under the SEPTA tracks and new water main construction on Tyson Ave.
Concrete curb preparation on Ardsley Avenue and concrete curb construction on Tyson Ave.
New concrete curb on the south side of Tyson Ave. at the West end of the project (both images below)
New roadway preparation on Tyson Avenue and stone subbase placement for new roadway on Tyson Ave.
May 2019
Work Performed to Date
As of April 30, 2019, the contractor is continuing with drainage installation on Tyson Ave. between Edge Hill Road and Bruce Ave. as well as on side roads between Tyson Ave. and Edge Hill Road. Placement of the final level of asphalt pavement is complete on Hillside Drive. The utility companies are continuing with relocation of water and gas mains as well as individual services to resident properties. Utility pole relocations have started on Edge Hill Road and Tyson Ave. as well as side roads.
Upcoming Work to be Performed
In May, the contractor will continue drainage construction on Tyson Ave. and the side roads between Tyson Ave. and Edge Hill Road. Drainage installation under the SEPTA railroad tracks will start. Water and gas main and utility pole relocations will continue. Curb and sidewalk construction will start on the south side of Tyson Ave. between Edge Hill Road and Bruce Ave. Traffic on sections of Tyson Ave. will be closed to all traffic except local traffic.
Drainage construction on the south side of Tyson Avenue and new asphalt pavement base on Hillside Road.
Drainage construction at Tyson Ave. at Edgecomb Road and utility relocation on Edgecomb Ave.
Drainage construction on Ardsley Ave. and drainage construction on the west end of Tyson Ave.
April 2019
Work Performed to Date
As of March 29, 2019, the contractor has completed drainage pipe installation in the Hillside Cemetery (Hillside Drive). Placement of the first level of asphalt pavement is complete on Hillside Drive. The contractor has started drainage installation on Tyson Ave. between Edge Hill Road and Edgecomb Road. The utility companies have started relocation of water and gas mains as well as individual services to resident properties. Drainage installation continues on the side roads between Tyson Ave. and Edge Hill Road.
Upcoming Work to be Performed
In April, the contractor will continue drainage on Tyson Ave. and the side roads between Tyson Ave. and Edge Hill Road. Drainage installation under the SEPTA railroad tracks will start. Water and gas main relocations will continue, and utility pole relocations will start in April. Traffic on sections of Tyson Ave. will be closed during daytime working hours to all traffic except local traffic.
Beyond April, drainage installation will continue on the south side of Tyson Road and paving of Hillside Drive will be completed.
Hillside Road asphalt and rock capping on drainage basin berm in Hillside Cemetery
Drainage outlet pipes north of SEPTA tracks and 30-in drainage pipe installation on Tyson Ave.
Inlet and 18-inch drainage pipe installation Tyson Ave. and utility relocation on Tyson Ave.
March 2019
Work Performed to Date
As of February 28, 2019, the contractor has installed 95% of the drainage facilities in the Hillside Cemetery (Hillside Road). The contractor has completed removal of the existing median on Tyson Avenue and placed temporary paving that will be used for future Traffic Control staging. The contractor has cleared trees required to allow for construction and installed construction access roads to the work area for proposed drainage under the SEPTA railroad tracks. Drainage installation has started on the side roads between Tyson Avenue and Edge Hill Road.
Upcoming Work to be Performed
In March, the contractor will complete drainage in the Hillside Cemetery and start paving of affected roads in the cemetery when the weather is warmer. Drainage under the SEPTA railroad tracks will start. Drainage construction will continue of the side roads between Tyson Avenue and Edge Hill Road and start on Tyson Avenue. Water and gas main relocations will start in March.
Beyond March, drainage installation will continue on the south side of Tyson Avenue. Traffic on Tyson Avenue will remain in both directions with traffic shifted to the north.
Temporary median paving on Tyson Road and drainage construction in Hillside Cemetery
Rock berm for drainage basin north of SEPTA tracks and tree removal
February 2019
Work Performed to Date
As of January 31, 2019, the contractor has installed 75% of the drainage facilities in the Hillside Cemetery (Hillside Road) and expects to complete this drainage by the end of February 2019. The contractor has started removal of existing median on Tyson Road and placed temporary paving that will be used for future Traffic Control staging. The contractor has cleared trees required to allow for construction and installed construction access roads to the work area for proposed drainage under the SEPTA railroad tracks.
Upcoming Work to be Performed
In February, the contractor will continue drainage in the Hillside Cemetery, start drainage under the SEPTA railroad tracks and continue with removal of the existing median on Tyson Road and placement of temporary pavement weather permitting.
Beyond March, drainage installation will start on the south side of Tyson Road after completion of the drainage under the SEPTA railroad tracks. Traffic on Tyson Road will remain in both directions with traffic shifted to the north.
Temporary median construction on Tyson Road and drainage construction north of SEPTA railroad tracks
Drainage construction in Hillside Cemetery and downstream drainage in Hillside Cemetery
Press Releases
This section will include press releases about the project including traffic restrictions. It will be updated as press releases are available.
11/01/2018: Wolf Administration Breaks Ground on Edge Hill Road/Tyson Avenue Improvement Project in Abington Township, Montgomery County, https://www.penndot.gov/RegionalOffices/district-6/pages/details.aspx?newsid=3861
3/13/2019: Tyson Avenue to be Restricted, Closed for Several Months for Drainage Improvement in Abington Township,https://www.penndot.gov/RegionalOffices/district-6/pages/details.aspx?newsid=4302
5/16/2019: Tyson Avenue Lane Closure for Drainage Improvement in Abington Township, https://www.penndot.gov/RegionalOffices/district-6/pages/details.aspx?newsid=4618
7/12/2019: Tyson Avenue Closure and Detour for Drainage Improvement in Abington Township, https://www.penndot.gov/RegionalOffices/district-6/pages/details.aspx?newsid=4873
"Tyson Avenue will be closed and detoured between Ardsley Avenue and Bradfield Road in Abington Township, Montgomery County on Monday, July 15, through the end of August, for drainage work on a project to improve safety and travel on Tyson Avenue, Edge Hill Road, Jenkintown Road and several adjacent township roads, the Pennsylvania Department of Transportation (PennDOT) announced today.
During the closure, Tyson Avenue motorists will be detoured over Edge Hill Road and Easton Road. Local access will be maintained up to the construction zone.In addition to the closure and detour, Tyson Avenue will be reduced to a single lane between Edge Hill Road and Ardsley Avenue.
Motorists are advised to allow extra time when traveling near the work area because backups and delays will occur."